Sea Ray Drive Water Transmission Main Relocation at Sykes Creek

The existing 36-inch water transmission main along Sea Ray Drive in Merritt Island conveys potable water to east Merritt Island and beachside customers by crossing Sykes Creek. Originally installed on the bridge above the creek, the water main is being relocated to a subaqueous crossing of the creek due to bridge renovations.

Status Construction
Design Start October 2021
Design Completion September 2022
Construction Start January 2023
Construction Completion November 2023
Spent Budget $331,051
Total Budget $5,040,283
Percent Construction Complete 1%
                                                                                                                                                                  Statistics as of March 2023