Michigan Ave Force Main

Installing approximately 2900 linear feet of 16" ductile iron (DI) pipe along Michigan Ave (from Clearlake Rd to US1). The existing pipeline along US1 acts as a single point of failure in the City's collection system.  After an analysis of the wastewater collection system, through a hydraulic model, a deficiency in this section was revealed. This can be resolved through this pipeline, creating a circular flow path.

Status Completed
Design Start April 2017
Design Completion October 2019
Construction Start February 2020
Construction Completion September 2020
Spent Budget $1,187,447
Total Budget $1,187,447
Percent Construction Complete 100%

Project Completed